Metals & Minerals News

Cadence ahead of schedule at Azteca

Cadence Minerals plc is ahead of schedule with the Azteca processing plant’s refurbishment at the Amapá iron ore project in northeast Brazil. The programme has reached some 48% weighted physical progress, compared with 41% planned progress. Cadence said that as 2 July 2026, 21 activities were complete, 10 were in progress and 33 had yet […]

Metals & Minerals News

Cadence on schedule to start Azteca plant at Amapá

Cadence Minerals plc expects its Azteca processing plant to be begin operations by the end of August 2026 at the Amapá iron ore joint venture in northeast Brazil. LICENCE Personnel, equipment and site resources have arrived on schedule at the site, and refurbishment has started. The company said that works cover key processing systems, including […]