Cadence ahead of schedule at Azteca

Cadence Minerals plc is ahead of schedule with the Azteca processing plant’s refurbishment at the Amapá iron ore project in northeast Brazil. The programme has reached some 48% weighted physical progress, compared with 41% planned progress. Cadence said that as 2 July 2026, 21 activities were complete, 10 were in progress and 33 had yet […]

Finance Metals & Minerals News

Cadence JV granted installation licence for Amapá

Cadence Minerals plc’s partner and operator DEV Mineração S.A. has received an installation licence (LI) for the Amapá iron ore project, including the restart of the Azteca plant, in northeast Brazil. PRODUCTION The LI covers approved works of refurbishment and replacement of existing operational structures, construction of new processing components – including magnetic separation, ball […]