Metals on course to assemble La India plant

Metals Exploration plc has unloaded the Rock Creek gold processing plant at a port in Nicaragua, ahead of delivery to the La India gold project site.

Target: gold production is due to begin by the final quarter of 2026 (Pixabay)

CONSTRUCTION

The plant arrived ahead of schedule and the start of assembly is on course for October 2025.

The company said that mine development earthworks, relating to the plant and the mine industrial area, are 95% complete, with the run-of-mine (ROM) pad being finalised.

Construction of site buildings and infrastructure is underway following the agreed “decamping of all artisanal miners from the project site and pit area”.

Chief executive officer Darren Bowden added that gold production was still due to start by the final quarter of 2026.